Bid bonds, performance bonds and insurance on Canadian tenders
Public construction tenders in Canada almost always require bonds, and nearly every public contract requires insurance. A bond is a guarantee from a surety company to the buyer that you will do what you promised. If you cannot provide the bonds a tender asks for, your bid is rejected, so arrange bonding before you bid, not after.
The bonds
- Bid bond. Submitted with the bid. It guarantees that if you are the low bidder you will sign the contract and provide the other bonds. Usually 10 per cent of the bid price. If you walk away, the surety pays the buyer the difference to the next bid, up to the bond amount, and then recovers it from you.
- Consent of surety (agreement to bond). A letter from the surety, also submitted with the bid, promising to issue the performance and payment bonds if you win.
- Performance bond. Provided when the contract is signed. It guarantees the work will be completed. Commonly 50 per cent of the contract price.
- Labour and material payment bond. Guarantees your subcontractors and suppliers will be paid. Also commonly 50 per cent of the contract price.
Some tenders accept a certified cheque, bank draft or irrevocable letter of credit in place of a bid bond. In Ontario, the Construction Act requires performance and payment bonds on public contracts of $500,000 or more.
How to get bonded
Bonds come from surety companies, through an insurance broker that handles surety. The surety reviews your business before it agrees to back you: financial statements (preferably prepared by an accountant), working capital, bank credit, work in progress and the experience of the people running the jobs. It then sets a bonding facility: a limit per project and a total across all bonded work. Expect the first approval to take a few weeks. Owners usually give a personal indemnity, which means the surety can recover a loss from them.
The bid bond itself costs little or nothing. Performance and payment bonds are priced as a percentage of the contract, and that cost belongs in your bid.
The insurance buyers ask for
- Commercial general liability, on almost every contract, commonly with a limit of $2 million or $5 million per occurrence and the buyer named as an additional insured.
- Automobile liability where vehicles are used for the work.
- Professional liability (errors and omissions) for engineers, architects, consultants and IT firms.
- Builder’s risk or installation coverage on construction, covering the work while it is being built.
- Workers’ compensation: a clearance certificate from the provincial board showing your account is in good standing.
The tender states the limits. Send the insurance section to your broker before you bid; raising a limit takes days, and the cost goes into your price. Bonds and insurance are among the mandatory requirements that decide whether a bid is read at all.
Questions
How much is a bid bond in Canada?
Usually 10 per cent of the bid price on public construction tenders. The tender documents state the exact amount or percentage.
What is the difference between a bid bond and a performance bond?
A bid bond is submitted with the bid and guarantees the bidder will sign the contract if it wins. A performance bond is provided at signing and guarantees the work will be completed, commonly for 50 per cent of the contract price.
Can a new or small contractor get bonded?
Often, yes, for smaller projects. A surety looks at financial statements, working capital and experience and sets a limit to match. Start the application through a surety broker a few weeks before the first tender you want to bid.